Little Cedars Elementary School /
New Elementary School Update

Here is the address for the live Webcam for the construction project! http://www.lydig.com/ses. 

This page updated: June 1, 2007

What has happened at the new elementary school site this month?

  • Crews have been installing underground water and sewer lines.  (See photo below, dated May 24, 2007).

 

  • Crews are widening Cathcart Way and installing traffic signals.  (See photo below, dated May 24, 2007).

 

  • The Multipurpose Room and Gymnasium are being painted.  (See photo below, dated May 24, 2007).

 

  • Cabinets and carpet are being installed in the Library.  (See photo below, dated May 24, 2007).

 

  • Cabinets and carpet are also being installed in the Administration Areas.  (See photo below, dated May 29, 2007).

 

  • Crews have installed cabinets in the Staff Lounge.  (See photo below, dated May 29, 2007).

Other projects that have been completed:

  • Storefronts and glazing
  • Hung doors and installed door hardware
  • Paint and ceiling grid in Music Room
  • Ceramic tile and toilet fixtures in all bathrooms
  • Installed toilet partitions.
  • Siding of exterior walls of the Academic Building.

 What will happen in the coming weeks at the new elementary school site?

  • Sidewalks and asphalt paving on Cathcart Way.
  • Curbs, gutters and sidewalks on 144th Pl SE.
  • Complete water and sewer underground utilities.
  • Place and finish concrete stairs, walls and sidewalks in the Courtyard Area.
  • Complete interior lighting, Heating and plumbing work.
  • Complete paint, carpeting, toilet accessories and cabinet work.
  • Install Smartboards, sound enhancement systems and ceiling mounted projectors.
  • Install siding on Activities Building.


 


Please select a date below for a PDF version of the weekly "New Elementary School Construction Update."

April 27, 2007
April 6, 2007
March 2, 2007
February 2, 2007
January 26, 2007
January 19, 2007
January 12, 2007
January 5, 2007
December 15, 2006
December 8, 2006
December 1, 2006 - No update due to weather conditions.
November 24, 2006 - No update due to the holiday
November 17, 2006
November 10, 2006 - No update due to weather conditions.
November 3, 2006
October 27, 2006
October 20, 2006
October 13, 2006
October 6, 2006
September 29, 2006
September 22, 2006
September 15, 2006


Questions? Please contact the Capital Projects Office at:
360-563-7360.

 